PROCEDURE FOR BUILDING APPLICATION
.  

Checklist:
A) Application forms.
B) Ownership Certificate.
C) Official site plan.
D) Registration/Certificate of the Designer.
E) Three sets of Drawings:-
   - Three sets of Architectural drawings.
   - Three sets of Structural drawings.
   - Three sets of Electrical drawings.
   - Three sets of Sewerage connection drawings.
   - Three sets of telephone connection drawings
F) Format of the drawings:-
   - Name of Project.
   - Owners Signature
   - Designers Signature
   - North Direction
   - Scale of drawings.

Notes:
1. Every application must be accompanied by this completed form.
2. Signing on behalf of the applicant is not permitted unless there is the power of attorney / Authorization.
3. For information, which is not applicable, please write in “not applicable” or “N/A”.
4. The responsibility of relocating any municipal services rests with the applicant.
5. For any cases involving additions, extensions or alterations the following will apply:
   a) A letter from a structural engineer is to be submitted certifying that the existing foundations are capable of taking the additional loads.
   b) A letter from a services engineer is to be submitted certifying that the existing septic tank is able to deal with the additional waste or
   c) A new septic tank (duly marked on the site plan) is to be designed to take the additional waste.
   d) A non-destructive testing machine results/reports should be included to assess the stability of the existing structure.
   e) The existing building fabric is to be clearly identified on the drawings, and the existing setbacks and structure are to be verified as accurate by the applicant.

7. All applications should be accompanied by the appropriate documentation as required by the current Building Rules
8. Please use additional paper to give further information if necessary.

For more info, Please contact Architectural Unit at: 02-322265/325210(Extension: 121)